Bhubaneswar Municipal Corporation is set to celebrate Local Self-Government Day in a big with an array of projects ready for launch and foundation stone laying ceremonies lined up for Wednesday. A day ahead of the event, Sandeep Mishra of The Telegraph finds out the status of major projects initiated on this day in the past two years

TT Bureau Published 31.08.16, 12:00 AM

Bhubaneswar Municipal Corporation is set to celebrate Local Self-Government Day in a big with an array of projects ready for launch and foundation stone laying ceremonies lined up for Wednesday. A day ahead of the event, Sandeep Mishra of The Telegraph finds out the status of major projects initiated on this day in the past two years

The kalyan mandap where the BMC office is supposed to come up at Unit-VIII

Project: BMC office at Unit-VIII
♦ Foundation stone laid: 2015
♦ Cost: Rs 40 crore
♦ Status: No development
♦ Official reason: Opposition from local residents

The daily market at Unit-I

Project: Unit-I daily market renovation
♦ Foundation stone laid: 2015
♦ Cost: Rs 105 crore
♦ Status: 40 govt quarters demolished, eviction drive pending
♦ Official reason: Protests by vendors operating at the site

The land earmarked for a hospital at Gadakana

Project: Multi-specialty hospital at Gadakana
♦ Foundation stone laid: 2015
♦ Cost: Rs 255 crore
♦ Status: No development. Bhubaneswar Municipal Corporation organised an investors’ meet and a road show at Hyderabad recently to lure investors
♦ Official reason: Firm that had evinced interest gave up on the project a few months ago

Project: Modern slaughterhouse at Gadakana
♦ Foundation stone laid: 2015
♦ Cost: Rs 6.40 crore
♦ Status: No development
♦ Official reason: Sustained opposition from residents and delay in selecting bidder

...and three successes

The under-construction Rajiv Awas Yojana complex at Chandrasekharpur

Project: Rajiv Awas Yojana to rehabilitate slum-dwellers of Mandap Basti and Munda Sahi at Chandrasekharpur
♦ Foundation stone laid: 2014
♦ Cost: Rs 30 crore
♦ Status: Two of the five blocks are nearly complete. Tender has been invited to construct the remaining three blocks
♦ Officials say: Work is going on schedule. It is slated to finish by the end of this year

A water ATM near Sishu Bhavan Square

Project: Water ATMs
♦ Project announced: 2014
♦ Cost: Rs 12.5 lakh each
♦ Status: Ready

The newly inaugurated foot overbridge at Jayadev Vihar 

Project: Foot overbridge
♦ Foundation stone laid: 2013
♦ Cost: Rs 3 crore
♦ Status: Ready

Pictures by Ashwinee Pati