Adanis, NTPC defer green goal

Their move comes at a time when the country is battling rampant pollution

Reuters New Delhi Published 07.01.20, 07:19 PM
An Adani power project

An Adani power project Source: Adani Power Annual Report

Top Indian coal-fired power generators Adani Power and NTPC have sought two-to-three-year extensions of deadlines to install emissions-cutting equipment at some plants, according to documents reviewed by Reuters, even as the country battles rampant pollution.

The requests mean the two biggest power producers in India are pressuring the government to delay emissions targets for a second time, citing costs and technical difficulties, even as the country chokes on some of the worst smog on the planet.

ADVERTISEMENT

Highlighted in correspondences over the past year reviewed by Reuters, the requests haven’t previously been made public. They could set battle lines between the power industry and the environment ministry ahead of a key Supreme Court case on power plant emissions due in February.

India already extended its original December 2017 deadline for utilities to meet tighter new emissions standards, after extensive lobbying by the coal-fired power industry. The country now has a has a phased timetable — from end-2019 to end-2022 - and many coal-fired plants around New Delhi are operating despite missing deadlines, and want a further extension.

Adani Power wants to extend the timeline for stricter emissions rules at two units in a central Indian plant by about three years to March 2023, citing a change of ownership, the documents show. Adani bought the assets from the GMR group last year.

“It is requested to kindly extend the flue-gas desulphurisation (FGD) installation schedule for Raikheda thermal power plant of GMR Chhattisgarh Energy to March 31, 2023,” Adani said in a letter addressed to the federal pollution regulator in July. FGD equipment is used to reduce emissions of gases known to cause lung diseases.

Neither Adani nor the regulator responded to requests for comment on the extension application, which is still being considered by the environment ministry.