BCPL makes 96 % progress

Dibrugarh, June 5: Nearly 96 per cent progress has been made on the Brahmaputra Cracker and Polymer Limited (BCPL) at Lepetkata in Dibrugarh.

BCPL managing director P.N. Prasad said the cost of setting up the petrochemical plant has risen up to Rs 8,912.83 crore as against the approved of Rs 8,920 crore.

The plant will be completed by the end of August 2014 and, thereafter, a minimum period of six months will be required for commissioning.

The polymer production will begin from the next financial year.


 More stories in Northeast

  • Jorhat retail chain asked to compensate for buiscuits
  • Tarapur defeat Arunachal
  • Focus on governance
  • BCPL makes 96 % progress
  • Six girls in top 10 in Tripura
  • Saplings to be planted in Dhubri
  • Tinsukiaand MCC triumph
  • Go-green message on Environment Day
  • Child prodigy still untraced
  • Tall grass to check landslide
  • Meghalaya for efficient technology
  • Assam rowers in final
  • South Point in semis
  • Village pledges to conserve nature
  • Stress on ways to save water
  • Move to resolve college row